Solarpark Wyandot Solar

Capacity:
12 MW
Country:
United States
State:
Ohio
Commissioning:
2010
Modules:
159200

juwi developed, designed and built the Wyandot Solar Energy Facility, a 12.0 MWp solar PV facility located in Upper Sandusky, Ohio. In June 2009 juwi’s subsidiary executed a 20-year PPA with AEP Ohio. Construction commenced in the fourth quarter of 2009, and the project achieved commercial operation in May 2010.

  • juwi’s construction group, together with a leading Ohio-based subcontractor, commenced construction in October 2009
  • Includes 159,200 ground-mounted, thin-film solar panels on 77-acre plot of land
  • Commercial operation occurred on May 26, 2010
  • In September 2009, juwi transferred its ownership rights in the project to PSEG Solar Source
  • Energy and REC off-taker is AEP Ohio
  • juwi is currently operating, maintaining and monitoring the project on behalf of PSEG Solar Source

More topics

Newest article

Largest single project in the history of the joint venture: juwi Shizen Energy connects 54-megawatt solar park to the grid in Japan

The solar power plant is located on a former golf course about 100 kilometers north of Tokyo. more

juwi Operations & Maintenance GmbH expands range of services to include maintenance for large-scale battery storage systems

Service offering for large-scale battery storage systems includes maintenance, repair and… more

juwi commissions largest bi-facial solar power plant of Europe

In the Greek city of Kozani, juwi made an important contribution to the transformation of energy… more