Capacity:
13.09 MW
Annual Yield:
20.99 mil. kWh
Country:
United States
State:
Maryland
Commissioning:
2015
Modules:
42240

The 13.09 MWp Rockfish Solar project is scheduled to achieve commercial operation by June of 2015. Rockfish Solar, located in Waldorf, Maryland, was developed and construction by juwi. The Southern Maryland Electrical Cooperative (SMECO) will purchase all of the electricity and environmental attributes from the facility for 20 years pursuant to a power purchase agreement. The solar project is owned by PSEG and consists of 42,240 photovoltaic modules on an approximately 69-acre site.

  • Construction began in January 2015
  • Commercial operation Q2 2014
  • Includes approximately 42,240 crystalline-silicon solar panels on a single-axis tracking system
  • 69-acre site
  • Owner is PSEG Solar
  • Annual generation 20,987 MWh
  • juwi will operate and maintain the project in the initial years

More topics

Newest article

juwi to construct world’s largest solar hybrid project at an off-grid mine for Centamin in Egypt

The 36MW solar farm and a 7.5 MW battery-energy storage system will tangibly reduce CO2 emissions of… more

juwi to construct 13.6MWp solar farm for APA at the Gruyere Gold Mine

The solar farm and a 4.4 MW battery-energy storage system will be integrated into the existing APA… more

First module rows installed at Europe’s biggest bifacial solar park

In Northern Greece, the juwi group is building a 204 megawatt (MW) solar park for the Hellenic… more