Solarpark Wyandot Solar

Capacity:
12 MW
Country:
220
State:
Ohio
Commissioning:
2010
Modules:
159200

juwi developed, designed and built the Wyandot Solar Energy Facility, a 12.0 MWp solar PV facility located in Upper Sandusky, Ohio. In June 2009 juwi’s subsidiary executed a 20-year PPA with AEP Ohio. Construction commenced in the fourth quarter of 2009, and the project achieved commercial operation in May 2010.

  • juwi’s construction group, together with a leading Ohio-based subcontractor, commenced construction in October 2009
  • Includes 159,200 ground-mounted, thin-film solar panels on 77-acre plot of land
  • Commercial operation occurred on May 26, 2010
  • In September 2009, juwi transferred its ownership rights in the project to PSEG Solar Source
  • Energy and REC off-taker is AEP Ohio
  • juwi is currently operating, maintaining and monitoring the project on behalf of PSEG Solar Source

More topics

Newest article

juwi signs agreement with EDL to deliver Hybrid Project at Gold Fields Agnew Mine site in Australia

The project consists of a 4 MW Single Axis Tracking PV installation together with cloud forecasting... more

Sandfire DeGrussa hybrid project delivers record production

Project achieved its annual generation targets one month ahead of schedule. more

juwi builds 82MWp Solar Park in Colorado for US-Renewable Energy Provider Duke Energy Renewables

Utility-scale project will provide clean energy to customers of Colorado Springs Utilities. more